Construction Material Calculator

How much cement, steel, bricks and sand will your house need? Enter the built-up area and get quantities instantly — then add your local prices to see the material bill.

Total of all floors. A 30×40 plot with G+1 is roughly 2,000 sq ft.

Finish quality

Estimated quantities

For 1,000 sq ft · standard finish

Cement

50 kg OPC/PPC bags — concrete, brickwork and plaster

400 bags
₹

Steel (TMT bars)

8–16 mm TMT for slabs, beams, columns, footings

4,000 kg
₹

Bricks

Standard red clay bricks for 230 mm / 115 mm walls

9,350 nos
₹

Sand

River sand or M-sand for concrete, mortar and plaster

1,600 cft
₹

Aggregate (gitti)

20 mm crushed stone for RCC concrete

1,350 cft
₹

Flooring tiles

Includes ~10% for cutting and breakage

1,100 sqft
₹

Paint

Interior walls, two coats

7.2 litres
₹

Enter prices from your local dealer to see the material bill.

How this calculator works

Indian site engineers estimate materials for a regular RCC-frame house using per-square-foot thumb rules, derived from standard concrete mixes in IS 456:2000 and typical brick-masonry practice. This calculator applies the same rules to your built-up area — the total covered area of all floors, not the plot size.

MaterialThumb rule (per sq ft built-up)
Cement≈ 0.4 bags (50 kg)
Steel≈ 4 kg
Sand≈ 1.6 cft
Aggregate≈ 1.35 cft
Bricks≈ 8.5 per sq ft of wall (wall area ≈ 1.1× built-up)

A basic finish uses about 8% less material and a premium finish about 12% more (thicker tiles, extra paint coats, more plaster work).

Built-up area vs plot area

Most mistakes come from using the plot size. A 30×40 ft plot is 1,200 sq ft, but after setbacks you may build only ~1,000 sq ft per floor — so a ground-plus-one house is about 2,000 sq ft of built-up area. Use that total here.

Where quantities change the most

  • Steel rises sharply for long spans, cantilevers, basements, G+2 and above, or weak soil — always follow your structural engineer's drawings.
  • Bricks depend on how many internal walls you have; AAC blocks or fly-ash bricks change the count entirely.
  • Sand and aggregate are sold in different units across states (cft, brass, tonne). One brass = 100 cft.

Using this to check a contractor's quote

Ask the contractor for their material quantities and compare them with these figures. If cement or steel is more than 15–20% higher without a structural reason, ask why. If it is much lower, check that the specification (concrete grade, bar sizes) hasn't been cut.

Frequently asked questions

How many cement bags are needed for a 1000 sq ft house?

About 400 bags of 50 kg cement for 1,000 sq ft of built-up area with a standard finish (≈0.4 bags per sq ft). This covers RCC concrete, brickwork mortar and plaster. Add 5–10% for wastage.

How much steel is required for a 1000 sq ft house?

Roughly 4,000 kg (≈4.0 tonnes) of TMT steel — the common thumb rule of about 4 kg per sq ft for a ground-plus-one RCC house. Your structural engineer's bar bending schedule (BBS) gives the exact figure.

How many bricks are needed for a 1000 sq ft house?

Around 9,350 standard bricks, assuming wall area of roughly 1.1× the built-up area. Houses with more partition walls or 230 mm external walls throughout need more.

What materials are needed for a 1500 sq ft house?

For 1,500 sq ft (standard finish): ~600 cement bags, ~6,000 kg steel, ~14,025 bricks, ~2,400 cft sand and ~2,025 cft aggregate.

How accurate is this material calculator?

It uses standard Indian site-engineering thumb rules (based on IS 456 concrete mixes) and is typically within ±10% for regular RCC frame houses. It is meant for budgeting and comparing contractor quotes — not as a bill of quantities (BOQ). Basements, long spans, heavy loads or poor soil change quantities significantly.

Planning estimates only. Final quantities come from your architect's drawings and the structural engineer's bar bending schedule.